HOWTO get the Ceph lead to decide if it is time for a point release » History » Version 1
Loïc Dachary, 04/09/2015 01:53 PM
1 | 1 | Loïc Dachary | After all issues have been backported and tested, it is technically possible to cut a release and the Ceph lead must decide if it should be done. |
---|---|---|---|
2 | |||
3 | * Ask Sage Weil if the commits merged in the release branch "deserve a point release":http://ceph.com/docs/master/dev/development-workflow/#cutting-a-new-stable-release |
||
4 | * If the answer is *not yet*, then go back to [[HOWTO schedule an issue for backporting|scheduling issues for backporting]] |
||
5 | * If the answer is *yes*, then proceed to [[HOWTO get the leads to sign-off on a release|get the leads to sign-off on the release]] |