h3. Workflow 

 * "Preparing the release":http://ceph.com/docs/master/dev/development-workflow/#preparing-a-new-release 
 * "Cutting the release":http://ceph.com/docs/master/dev/development-workflow/#cutting-a-new-stable-release  
 ** Nathan asks Abhishek L. if a point release should be published - YES 20170801 
 ** Nathan gets approval from all leads 
 *** Yehuda, Matt, Casey, Orit rgw - YES 20170802 
 *** Patrick, CephFS - YES 20170801 ("go for it") 
 *** Jason, RBD - YES 20170801 ("long overdue") 
 *** Josh, rados - YES 20170801 ("sounds good") 
 *** Sage - YES 20170801 ("release what we have for 11.2.1") 
 ** Abhishek L. writes and commits the release notes - PENDING, see https://github.com/ceph/ceph/pull/16879 
 ** Nathan informs Yuri that the branch is ready for testing - DONE 20170802 
 ** Yuri runs additional integration tests - DONE 20170807 
 ** If Yuri discovers new bugs that need to be backported urgently (i.e. their priority is set to *Urgent*), the release goes back to being prepared, it was not ready after all 
 ** Yuri informs Alfredo that the branch is ready for release - DONE 20170807 
 ** Alfredo creates the packages and sets the release tag - DONE 

 h3. Release information 

 ** branch to build from: kraken, commit: 11d5c2b0aae372f9c993a7dea5a914ee74e7480c 
 ** version: v11.2.1 
 ** type of release: point release 
 ** where to publish the release: http://download.ceph.com/debian-kraken and http://download.ceph.com/rpm-kraken