Project

General

Profile

Tasks #19055

Updated by Ken Dreyer almost 7 years ago

h3. Workflow

* "Preparing the release":http://ceph.com/docs/master/dev/development-workflow/#preparing-a-new-release
* "Cutting the release":http://ceph.com/docs/master/dev/development-workflow/#cutting-a-new-stable-release
** Loic asks Abhishek L. if a point release should be published
** Loic gets approval from all leads
*** Yehuda, rgw
*** John, CephFS
*** Jason, RBD
*** Josh, rados
** Abhishek L. writes and commits the release notes
** Loic informs Yuri that the branch is ready for testing
** Yuri runs additional integration tests
** If Yuri discovers new bugs that need to be backported urgently (i.e. their priority is set to *Urgent*), the release goes back to being prepared, it was not ready after all
** Yuri informs Alfredo that the branch is ready for release
** Alfredo creates the packages and sets the release tag

h3. Release information

** branch to build from: jewel, hammer, commit: TBD, tentatively a64d3e4b33e904aa6585464df8ffff6aafdec10c TBD
** version: v10.2.7
** type of release: point release
** where to publish the release: http://download.ceph.com/debian-jewel and http://download.ceph.com/rpm-jewel