Total time: 20.50 hours

Project Date User Activity Issue Comment Hours
Ceph06/11/2013Loïc DacharyDevelopmentSubtask #5213: unit tests for src/osd/PGLog.{cc,h}discuss rewind_divergent_log border case0.50
Ceph06/08/2013Loïc DacharyDevelopmentSubtask #5213: unit tests for src/osd/PGLog.{cc,h}rewind_divergent_log tests case and question to the list2.00
Ceph06/02/2013Loïc DacharyDevelopmentSubtask #5213: unit tests for src/osd/PGLog.{cc,h}complete merge_old_entry unit tests and ask question about the rationale of a case3.00
Ceph05/31/2013Loïc DacharyDevelopmentSubtask #5213: unit tests for src/osd/PGLog.{cc,h}wrote part of the tests for merge_old_entry5.00
Ceph06/07/2013Loïc DacharyDevelopmentSubtask #5213: unit tests for src/osd/PGLog.{cc,h}writing merge_log tests5.00
Ceph06/17/2013Loïc DacharyDevelopmentSubtask #5213: unit tests for src/osd/PGLog.{cc,h}write unit tests for proc_replica_log5.00
    (1-6/6)